Development

 

La Ronge Gold Project

  • Golden Band has been moving forward with plans to be in production in 2010. Our business case builds on the long-term scenario from the base-case of conservative scoping study.
Development Objectives:
  • Produce 70,000 ounces per year from the 700 tonne per day Jolu mill using blended underground and open pit methods;
     
  • Focus in near-term to expand resource base to support
    a minimum 10-year production life; and
  • Continue long-term low-cost acquisition strategy targeting opportunities within the haulage distance of the mill.
What's been completed?

 

What needs to be completed in order to produce gold in 2010?

  • Production decision for four mines using the Company’s Jolu Mill:
    Based on Pre-feasibility Study.
     
  • Finance project: 
    Working capital plus project pre-production capital costs is estimated to be ~$22 million and
    the Pre-feasibility study that is now underway will update financial evaluation.
  • Continued Expansion of Resources:
    Assess opportunity for external sources of additional high grade mill feed through the Bingo extension, Greywacke and Golden Heart target zones.